# As-built LCA from your purchases: the BR18 climate calculation from supplier invoices

Guide · Updated 17 November 2026 · Written by DiFacto

Short answer

An as-built LCA under BR18 must show the materials actually used in the building, and your purchase invoices show them with item, quantity and unit. Each material line is converted to the data source's unit and to kilos, matched to an EPD or to the generic data in BR18 Annex 2, Table 7, and multiplied by the figures for each module. Waste belongs to the construction process (A5), and returned goods must be deducted. Other parties' purchases and the energy for operation and the site must come from other sources.

Many of the figures for the climate calculation under BR18, the Danish building regulations, are already on your supplier invoices: which item, how much and when. This guide shows how an invoice line becomes LCA data, what the invoices do not tell you, and what you have to supply yourself. The limit values and the indicative limits for 2027 and 2029 are in [BR18 LCA requirements](https://difacto.dk/en/guide/br18-lca-requirements), and in Danish on [BR18 og LCA](https://difacto.dk/br18-lca).

## What is an LCA under BR18, and when is it done?

LCA stands for life cycle assessment. Under section 297 of the building regulations, new buildings and extensions must have a calculation of the building's climate impact over its whole life cycle. There are exemptions, for example unheated buildings under 50 m² floor area, and extensions under 250 m² heated floor area to farmhouses, detached, terraced, linked and semi-detached houses and holiday homes (section 297(2) and (3)). Renovation without an extension is not covered.

The result is stated in kg CO2e per m² per year over 50 years from completion. The calculation and its assumptions must be documented on the building case at completion (section 40). According to the guidance from the Danish Authority of Social Services and Housing, the calculation must reflect the quantities and materials used in the building when it is finished and ready for use. The authority's guide for contractors calls it «as built»: the LCA must show the building as constructed. The documentation can be delivery notes and invoices for materials delivered to the site.

The building's life is divided into modules, from the manufacture of the materials (A1–A3) to disposal (C3–C4). They are explained in [the article on EPDs](https://difacto.dk/viden/epd-miljoevaredeklaration#livscyklussens-moduler-a1-a3-a4-a5-b-c-og-d) (in Danish). The construction process (A4–A5), that is transport to the site and energy and waste on the site, has one common limit, see [the climate requirements for the construction process](https://difacto.dk/viden/byggeprocessens-klimakrav) (in Danish).

## What the invoices show, and what they do not

The quantities in an LCA can be taken from drawings or from 2D and 3D BIM models. They can also come from what was actually bought. The supplier invoice shows the item number, item text, quantity, unit, supplier and date. The item number and text lead to the product and the manufacturer, and so to an EPD if there is one.

But the invoices are not the whole account:

- **Bought is not the same as built in.** Waste and offcuts are part of the purchase. They become construction waste and belong to the construction process (A5), not to the building's materials.
- **Returned goods must be deducted.** They appear on a credit note or as a minus line on the invoice.
- **One invoice can cover several jobs.** It can also have goods for the stock.
- **Other parties' purchases are not on your invoices.** That goes for the subcontractors' materials and the client's own deliveries. Cash purchases and goods from your own stock are missing too.
- **Operation and site energy are not on the material invoices.** The operational energy (B6) comes from the energy frame calculation. Diesel and site electricity are on fuel card and electricity invoices.
- **Parts not yet built must be included.** If the building is handed over as a shell, flooring, paint, tiles and whatever else is needed before it can be used must still be included. They are estimated from a best assessment, not from invoices.

## Step by step

### 1. Collect the invoices for the job

Collect all supplier invoices that belong to the job. Write the job number on every order, and ask the suppliers to carry it over to the invoice. Then it can be placed on the right job. If an invoice has goods for several jobs, note which lines belong to which job.

### 2. Remove what is not part of the building

Freight, fees, deposits and labour are not materials. Tools are not part of the building. Annex 2, Table 6, shows which building parts must be included in the calculation (section 297(6)). The table also gives examples of what is not included. Cable trays, switchboards, lighting, kitchen cabinets and loose furniture are marked «No». The same goes for the site's scaffolding and site huts. PV panels (photovoltaics) that count in the energy frame, and lifts, are marked «Yes».

### 3. Find the material and the data source

Determine what the item physically consists of: concrete, brick, plasterboard, timber, mineral wool and so on. Then find the figures. BR18 uses the state's [generic data](https://difacto.dk/ordbog/generiske-data) (in Danish) in Annex 2, Table 7, and a valid and relevant EPD can be used instead (section 297(7) and (8)). When an EPD can be used is described in [the article on EPDs](https://difacto.dk/viden/epd-miljoevaredeklaration#hvornaar-kan-epd-en-bruges) (in Danish). Note the data source for each line, so the figure can be traced.

### 4. Convert the quantity to the data source's unit and to kilos

The invoice states the quantity in pieces, metres, m², m³ or kg. Table 7 states each material per declared unit, for example 1 m³ or 1 m², and has a mass factor that says what the unit weighs. If the invoice says pieces or metres, the quantity is converted using the item's dimensions. «45x195» on a line in metres is thickness and width in mm. You can also use the weight for the transport to the site (A4), where Table 10 has rates per kg as an alternative to measured fuel. Table 11 states the waste treatment (A5) per kg.

### 5. Split the purchase into built in and waste

Deduct waste and offcuts from what was bought. What is built in counts as the building's materials. The waste becomes construction waste and counts in the construction process (A5). If goods have been returned, deduct them too.

### 6. Multiply the quantity by the figures for each module

Multiply the built-in quantity by the data source's figures for manufacture (A1–A3), waste processing (C3) and disposal (C4). Module D is calculated too, but is stated separately and does not count towards the limit. If a material must be replaced within the 50 years, the replacements count in B4. The service lives are in the BUILD service life table (BUILD Report 2021:32), which section 297(10) refers to.

### 7. Add the construction process and operation

The construction process is more than the materials: fuel, electricity and heating on the site and removal of waste and soil. The figures are in your fuel card, electricity and waste records, see [which figures the contractor must have ready](https://difacto.dk/viden/byggeprocessens-klimakrav#hvilke-tal-skal-entreprenoeren-have-klar) (in Danish). The operational energy (B6) is calculated from the building's calculated energy demand and the emission factors in Annex 2, Table 8.1 (section 297(11)). For buildings outside the energy frame, for example holiday homes and extensions, the state's standard values can be used (subsection 12).

### 8. Divide by the area, and hold the result against the limits

Materials, replacement and disposal are divided by the reference area and 50 years. The operational energy is divided by the heated floor area and 50 years. The construction process is also divided by the reference area and 50 years. Materials and operation together are held against the building's limit, and the construction process (A4–A5) is held against its own.

## Worked example: a line of ready-mixed concrete

The invoice says «Fabriksbeton C25/30 XC1» (ready-mixed concrete), 12 m³. Table 7 has a row for that type of concrete (#B1433), an industry EPD from EPD Danmark. It is stated per m³:

| Module                                    | kg CO2e per m³ | 12 m³ |
| ----------------------------------------- | -------------- | ----- |
| A1–A3 Manufacture                         | 241            | 2,892 |
| C3 Waste processing                       | 6.73           | 80.8  |
| C4 Disposal                               | 4.97           | 59.6  |
| D Recycling potential (outside the limit) | −4.6           | −55.2 |

The mass factor is 2,246 kg per m³, so the concrete weighs 26,952 kg. That is the weight the transport to the site (A4) is calculated on. If all 12 m³ are built in, the line contributes 3,032 kg CO2e to the building's materials (A1–A3, C3 and C4). Divided by a reference area of 1,000 m² and 50 years, that is 0.061 kg CO2e per m² per year.

A whole house, where the carpentry contract's invoice lines are worked through to kilos, data source and kg CO2e, is in [the worked example](https://difacto.dk/en/guide/as-built-lca-example).

## How DiFacto does it

DiFacto's climate calculation goes through the same steps for every job. It is an add-on to the subscription for companies in construction, and the price is in [the price calculator](https://difacto.dk/#priser) (in Danish). Invoices come in by upload, where you choose the job, or with the AutoPilot add-on via your own DiFacto email address, where the system suggests the job.

### What the system does

- Freight, fees, deposits and labour are removed. Items the system classifies as electrical equipment, furniture, fixings or sealant do not count.
- The system gives each item a material class, for example concrete, plasterboard or structural timber.
- Each material line is matched to a data source in this order: the product's EPD, an industry EPD and otherwise Table 7. The data source is shown on the line.
- The quantity is converted to kilos. If it is in kg, it is used as it is. Otherwise the system uses the item's weight per unit, or the dimensions in the item text and a fixed density for the material type. The kilos can therefore differ a little from Table 7's mass factor.
- The purchase is split into what is built in and waste, and the waste counts in the construction process.
- The transport of the materials to the site and the fixed items for the construction process are added with the state's rates.
- New invoices on the job update the calculation by themselves.

### What you supply yourself

- **The job.** Create the job as a project in DiFacto, and make sure the invoices are on it. An invoice belongs to one job.
- **The setup.** New building or extension, building type, reference area, heated floor area and the date of the application for the building permit. The application date decides which limit values the system uses. If the application is from 1 January 2027 or later, the system for now holds the project against the authority's indicative limits for 2027 and 2029. They are indicative and not finally decided. Without the heated area, the result is provisional.
- **The operational energy (B6).** The calculated energy demand from the energy frame calculation. You type it in or upload the report from the energy frame calculation (Be18) as a PDF. The system puts the figures in the fields as a suggestion, and you save them yourself. Holiday homes under 150 m² and extensions get the state's standard value until you type in other figures.
- **The site energy (A5).** Litres of diesel and kWh of electricity and district heating. If you upload a fuel card, site electricity or district heating invoice, the system suggests the quantities. There is no standard value for the site's energy. Without figures it counts as 0, and the result says that it is missing.
- **Removal of soil.** Turn the item on if soil is removed from the site as waste.
- **Materials that are not on your invoices.** You add cash purchases and goods from stock yourself, with a description, material type and quantity. They are clearly marked in the account. Materials delivered by other contractors or by the client are not part of your account. The party that compiles the calculation adds them.
- **Answers to questions.** If the weight or the environmental data for an item is missing, you get a question under «Mangler dig» (waiting for you), and the item does not count until you have answered. You can type the weight or the dimensions, and if you have an EPD for the item, you can upload it as a PDF. A weight applies to that one line only. An EPD applies to the item from then on.
- **The choice of standard values for plumbing.** If another contractor does the plumbing, you can choose the state's standard values for plumbing in the setup. Then your own plumbing lines do not count.

### What you get

- **The BR18 report as a PDF.** Summary, status against both limits, the modules and the materials, first per product category and then line by line with the data source.
- **The account as an Excel file.** Quantity, unit, mass in kg and data source for each line, the totals per module and a list of excluded and pending items. The PDF and the Excel file can be emailed to the consultant who does the overall calculation.
- **Sharing.** A share link gives another company that uses DiFacto read access to the account. If you are one of several contractors on the job, the party that compiles it all can see your part.
- **Status along the way.** The job is shown against both the building's and the construction process's limit. The result is rounded to one decimal before it is held against the limit. If something is missing, it says so next to it.

### What the climate calculation cannot do today

- It does not produce a file in an LCA program's own format, for example LCAbyg. The consultant gets the PDF and the Excel file.
- The materials are not divided into building parts such as external walls, floors and roof.
- The material classes are coarse. If an item has no EPD, all ready-mixed concrete is calculated as C25/30 and all steel as steel sheet, reinforcing steel included. Table 7 has more precise rows, so the consultant should check those lines.
- PV panels in the energy frame, lifts and platform lifts must be included under Table 6. The system has no material class for them, and electrical equipment does not count. They must be added in the consultant's calculation.
- Credit notes are not deducted, and the original line counts in full. A return line with a minus on an invoice is shown as a question and does not count. If an item has been returned, you can exclude the line and add the quantity that was built in with «Tilføj materiale» (add material).
- An invoice cannot be split between two jobs. If the invoice has goods for another job, exclude those lines. Add the materials on the other job with «Tilføj materiale».
- The system does not calculate the energy frame. The operational energy comes from the consultant's energy frame calculation.
- The state's standard value for operational energy is calculated as electricity, also with district heating. The operational energy is calculated from the year of application, not from the year the building is taken into use. Both give a higher figure, not a lower one.

The same invoices are also checked against your price agreements, see [the guide to checking supplier invoices](https://difacto.dk/en/guide/supplier-invoice-control). See also [DiFacto in English](https://difacto.dk/en).

## Frequently asked questions

### Can you do an as-built LCA under BR18 from purchase invoices?

Yes, for the materials that are on the purchase invoices. The invoice shows item, quantity and unit. Each material line can be converted to kilos and matched to an EPD or to the state's figures in BR18 Annex 2, Table 7. Bought is not the same as built in. Waste counts in the construction process (A5), and returned goods must be deducted. Materials bought by others, the operational energy and the site energy must come from other sources.

### When must the climate calculation be submitted?

The calculation and its assumptions are documented on the building case at completion, under BR18 section 40. According to the guidance from the Danish Authority of Social Services and Housing, it must reflect the quantities and materials used in the building when it is finished and ready for use.

### How do you convert an invoice line to kg CO2e?

Find the material and the data source, convert the quantity to the data source's unit and to kilos, and multiply by the figures for each module. In Table 7 (row #B1433), ready-mixed concrete C25/30 has 241 kg CO2e per m³ in A1–A3, so 12 m³ gives 2,892 kg CO2e. The transport to the site and the waste are calculated on the weight.

### What do we supply ourselves for the climate calculation in DiFacto?

The job with the invoices on it, building type, reference area, heated floor area and application date. Also the operational energy from the energy frame calculation, litres of diesel and kWh from the site, and cash purchases and goods from stock. If the weight or the environmental data for an item is missing, you get a question.

### Can the climate calculation be sent directly to LCAbyg?

No. The climate calculation does not produce a file in LCAbyg's own format. The consultant gets the BR18 report as a PDF and the account as an Excel file with quantity, unit, mass and data source for each line.

### Do returned goods and credit notes count?

Goods that have been returned are not built in and must be deducted from what was bought. In DiFacto, credit notes are not deducted today, and the original line counts in full. A return line with a minus on an invoice is shown as a question and does not count. You can exclude the original line and add the quantity that was built in as a material without an invoice.

## Sources

- [BR18 sections 297–298: Climate impact (in Danish)](https://www.bygningsreglementet.dk/tekniske-bestemmelser/11/krav/297%5F298/) — Danish Authority of Social Services and Housing (bygningsreglementet.dk)
- [Guidance on the climate impact of buildings (1 July 2025), section 1.1: buildings covered and documentation at completion (in Danish)](https://www.bygningsreglementet.dk/tekniske-bestemmelser/11/brv/bygningers-klimapaavirkning-1-juli-2025/kap-1%5F1/) — Danish Authority of Social Services and Housing (bygningsreglementet.dk)
- [Guidance on the climate impact of buildings (1 July 2025), section 1.2: life cycle, reference period and areas (in Danish)](https://www.bygningsreglementet.dk/tekniske-bestemmelser/11/brv/bygningers-klimapaavirkning-1-juli-2025/kap-1%5F2/) — Danish Authority of Social Services and Housing (bygningsreglementet.dk)
- [Guidance on the climate impact of buildings (1 July 2025), section 1.4: building parts, quantities and shells (in Danish)](https://www.bygningsreglementet.dk/tekniske-bestemmelser/11/brv/bygningers-klimapaavirkning-1-juli-2025/kap-1%5F4/) — Danish Authority of Social Services and Housing (bygningsreglementet.dk)
- [Guidance on the climate impact of buildings (1 July 2025), section 1.7: construction process (in Danish)](https://www.bygningsreglementet.dk/tekniske-bestemmelser/11/brv/bygningers-klimapaavirkning-1-juli-2025/kap-1%5F7/) — Danish Authority of Social Services and Housing (bygningsreglementet.dk)
- [The role of the contractor and the tradesperson in the climate requirements of the building regulations (revised December 2024, in Danish)](https://sbst.dk/Media/638731488482376925/VCBK%5FEntreprenorer%5Fopt-a%5B1%5D.pdf) — Danish Authority of Social Services and Housing (sbst.dk)
- [Annex 2, Table 6: Building parts for calculating climate impact (with Excel file, in Danish)](https://www.bygningsreglementet.dk/bilag/b2/bilag%5F2/tabel%5F6/) — Danish Authority of Social Services and Housing (bygningsreglementet.dk)
- [Annex 2, Table 7: Generic data (with Excel file, row #B1433, in Danish)](https://www.bygningsreglementet.dk/bilag/b2/bilag%5F2/tabel%5F7/) — Danish Authority of Social Services and Housing (bygningsreglementet.dk)
- [Annex 2, Tables 10 and 11: energy, transport and waste in the construction process (in Danish)](https://www.bygningsreglementet.dk/bilag/b2/bilag%5F2/?Layout=ShowAll) — Danish Authority of Social Services and Housing (bygningsreglementet.dk)
- [What is LCAbyg? (in Danish)](https://www.lcabyg.dk/) — LCAbyg ApS

[Læs guiden på dansk](https://difacto.dk/guide/lca-ud-fra-indkoeb)

---

Source: https://difacto.dk/en/guide/as-built-lca · Updated 2026-11-17 · DiFacto ApS